TEİAŞ Project About to Complete

Teias

Maltepe-Küçükbakkalköy project, Demirer Kablo’s 4th 380 kV TEİAŞ project in last 6 years, is now on the way to finalization. HVAC test will be performed between 26-31 March, 2013 and temporary acceptance certificate is expected to be recieved on the first week of April.

Starting the site works on June 2012, Demirer Kablo have laid 32 km 380 kV 1x2000 mm2 cable, have installed 42 joints and 6 GIS terminations. Total project amount was approximately 26,8 MUSD.